PROJECT UPDATES

Metro Project Updates

Construction Schedule (Updated on: 15-May-2017)

Corridor I Miyapur to LB Nagar
Stage 2 Miyapur to S R Nagar
Stage 5 S R Nagar to L B Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

Projects Updates

STAGEWISE DETAILS

Stage TOTAL KMS TOTAL PIERS TOTAL STATIONS
Stage-1 8.01 315 7
Stage-2 11.90 456 10
Stage-3 8.25 305 6
Stage-4 11.03 432 10
Stage-5 17.31 652 17
Stage-6 10.06 371 9
Total 66.56 2531 59

FOUNDATIONS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 305 245 60 100.0% 8.25
Stage-4 432 384 290 94 88.9% 9.73
Stage-5 652 648 478 170 99.4% 17.19
Stage-6 371 317 230 87 85.4% 8.41
Total 2531 2425 1844 581 95.8% 63.49

PIERS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 304 244 60 99.7% 8.22
Stage-4 432 378 284 94 87.5% 9.55
Stage-5 652 645 475 170 98.9% 17.09
Stage-6 371 255 176 79 68.7% 6.61
Total 2531 2353      1780 573 92.97% 61.38

SPAN ERECTION

Stage ERECTED Actual in VIADUCT Actual in STATION KMS
Stage-1 314 251 63 8.01
Stage-2 455 365 90 11.90
Stage-3 292 238 54 7.87
Stage-4 274 193 81 6.69
Stage-5 600 456 144 15.91
Stage-6 148 96 52 3.71
Total 2083 1599 484 54.09

SEGMENTS CAST

Casting Yard Casting Yard Name Segment Cast Scope No. Segment Cast Nos. Cast % KMs Complete
1 Uppal 16500 14588 88.41% 43.76
2 Qutubullahpur 8423 8423 100.00% 25.27
Total   24923 23011 92.33% 69.03