PROJECT UPDATES

Metro Project Updates

Construction Schedule (Updated on: 31-Mar-2017)

Corridor Number Corridor Details
Corridor I Miyapur to LB Nagar
Stage 2 Miyapur to S R Nagar
Stage 5 S R Nagar to L B Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

Projects Updates

STAGEWISE DETAILS

Stage TOTAL KMS TOTAL PIERS TOTAL STATIONS
Stage-1 8.01 315 7
Stage-2 11.90 456 10
Stage-3 8.25 305 6
Stage-4 11.03 432 10
Stage-5 17.31 652 17
Stage-6 10.06 371 9
Total 66.56 2531 59

FOUNDATIONS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 305 245 60 100% 8.25
Stage-4 432 380 286 94 88.0% 9.61
Stage-5 652 646 477 169 99.1% 17.14
Stage-6 371 305 222 83 82.2% 8.11
Total 2531 2407 1831 576 95.1% 63.02

PIERS COMPLETE

Stage TOTAL PIERS Actual TOTAL Actual in VIADUCT Actual in STATION % Complete KMS
Stage-1 315 315 245 70 100.0% 8.01
Stage-2 456 456 356 100 100.0% 11.90
Stage-3 305 302 242 60 99.0% 8.16
Stage-4 432 365 281 84 84.5% 9.33
Stage-5 652 633 473 160 97.1% 16.89
Stage-6 371 243 172 71 65.5% 6.37
Total 2531 2314 1769 545 91.43% 60.67

SPAN ERECTION

Stage ERECTED Actual in VIADUCT Actual in STATION KMS
Stage-1 314 251 63 8.01
Stage-2 455 365 90 11.90
Stage-3 279 225 54 7.48
Stage-4 254 183 71 6.26
Stage-5 572 438 134 15.22
Stage-6 144 96 48 3.65
Total 2081 1558 460 52.52

SEGMENTS CAST

Casting Yard Casting Yard Name Segment Cast Scope No. Segment Cast Nos. Cast % KMs Complete
1 Uppal 16500 14356 87.01% 43.04
2 Qutubullahpur 8423 8423 100.00% 25.27
Total   24923 22671 90.96% 68.34